top of page

Continental Villages’ Phase II Horizontal Construction Began

Updated: Sep 25, 2023


Horizontal Construction Began at Continental Village Phase II

We’ve begun horizontal construction on Phase II of Continental Villages. The sewer has been installed and the storm drain is under construction. Upon completion of the storm drain, installation of potable and fire water will follow. Dry utilities are scheduled to be installed during the late summer or early fall months. We received approval on building plans and routed to obtain building permits. In consideration of the project’s overall return on investment, Continental East Development decided to move forward with constructing the entire multifamily component at once rather than building it in phases. CED is currently working to secure a construction loan for vertical construction.


To learn more about Continental Villages, visit Continental East – Fund III, LLC.


42 views0 comments

Recent Posts

See All
bottom of page